Reinforcement for a new plant building

Client: Plasmore Ltd – Fixing Reinforcement.

We was instructed by Plasmor to place and fix reinforcement for a new plant building at their Knottingley site.

Method:

Fixing of 25.47 tons of High Yield Steel.

The rebar was fixed in accordance with the architectural drawings to lines and levels determined on site. This took a team of 4 men 2-3 weeks to complete the works.